Ansaldo Energia SpA
According to their 2020 Consolidated Financial Statement, production activities are occuring in Iran: "The AE94.3A gas turbine for the second unit at Dalahoo was rendered operational during the second half of the year, and the supervision of the steam turbine’s assembly is currently under way. The Heris AE94.3A gas turbine has been commissioned, and the preliminary acceptance of the entire project has been obtained. The completion and commissioning of the combined cycle at the Mazandaran and Heris sites is currently under way, both of which are expected to be completed during 2021. The following were shipped: the AE94.3A gas turbine destined for the Butia power plant and the main machine auxiliaries; several auxiliaries will be sent during the first months of 2021."
--
"Iran will operate two combined cycle power plants with production capacity of 500 megawatt in cooperation with an Italian energy company and a Russian bank... The Iranian MAPNA Group and the Italnian Ansaldo Energia Company has joined in design and FS research while the EXIMBank of Russia will provide 500 million," said Hasanali Taghizadeh, Trend reports citing ILNA." (Trend, "Iran to operate power plant in cooperation with Italy and Russia," 11/11/2019).
--
Company CEO said that he disagrees with sanctions, but "the sanctions we must close or suspend contracts." The firm will retain an office in Iran, however." (“Non ce ne andiamo da qui speriamo nella diplomazia (We’re not leaving here; let’s hope for diplomacy),” La Repubblica (Italy), August 8, 2018.)
--
In October 2017 Ansaldo Energia signed a MoU with several subsidiaries of the Iran state oil company NIOC on using natural gas that is being burned off in South Pars Gas Field Phase 12 in the Persian Gulf for electricity generation.
--
Ansaldo Energia appears to maintain an office in Tehran.
--
CEO of Ansaldo Energia, Giuseppe Zampini, presented at the Iranian Petroleum and Energy Club (IPEC) Congress, held October 19-21, 2015. (IPEC Congress 2015 Program)
--
May 17, 2013 Ansaldo Energia's Tehran branch manager Ido Picchioni was conferred the "Star for the Merit of Work" and thereby given the honorific "Master of Work," by the Italian President. (Quirinale, "Le Onorificenze della Repubblica Italiana," 5/17/13)
--
Ansaldo Energia owes "estimated income taxes (€ 10,077 thousand) for the activities carried out in Iran and not yet settled with local tax authorities." (2012 Annual Report)
--
"The Ansaldo Energia SpA unit of Italy's Finmeccanica SpA has contracts to supply 44 gas turbines to Iran, which will provide more than 20% of Iran's total energy production, according to the power-engineering company's web site. The number of gas-turbine units supplied has grown from an initial 32 in 1999." (The Wall Street Journal, "Iran's Energy Riches Lure European Firms," 7/12/07)
--
"'The last (sixth) phase of the Shirvan Gas Power Plant, in northeastern Iran, has been synchronized with the nationwide power grid. The turbines of the power plant are of A94/V2 kind -- joint products of Iran Power Plant Projects Management Company (MAPNA) and Italian company Ansaldo Energia,' he said." (Mehr News Agency, "New gas power plant comes on line in Iran," 5/9/07, As Translated By BBC Worldwide Monitoring)
--
Ansaldo Energia has offices in Damavand, Parand, Sanandaj, Shirvan, South Esfahan, and Teheran in Iran. (Company website)
"My decision is to follow your request to cancel Ansaldo Energia planned participation in the Italy-Iran Summit 2018 of next Dec 13th." (December 1, 2018)
Receive Iran News in Your Inbox.
Eye on Iran is a news summary from United Against Nuclear Iran (UANI), a section 501(c)(3) organization. Eye on Iran is available to subscribers on a daily basis or weekly basis.